Change orders and unexpected work in remodeling: how to document and approve them before executing

How to keep extra work on a remodel from eating your margin: a 4-step change order workflow with photo evidence, pricing and signature before executing.

In this article
  1. Why unapproved extra work drains project margins
  2. Hidden technical issues vs. client scope changes
  3. The 4-step protocol to approve change orders without friction
  4. 1. Document the finding or request on the spot
  5. 2. Price direct cost, overhead and schedule impact
  6. 3. Send a one-page change order marked “Pending approval”
  7. 4. Get it signed on the phone before executing
  8. How we handle it in Obrity
  9. Key takeaways

In residential and commercial remodeling, profit rarely disappears in the initial estimate: it disappears in the extra work done in good faith that was never formalized.

The scene plays out on almost every job site: the homeowner visits during demolition and says, “while we’re at it, let’s move this wall and add two recessed lights in the study.” The site manager agrees to keep momentum going, buys the materials, pays the crew, and two months later—when presenting the final invoice—the client replies: “I thought that was included.”

Why unapproved extra work drains project margins

What happens on siteWhy it happensConsequence at closeout
Client asks for a change verbally during a walkthroughNo change-order template on handOwner forgets the agreement or assumes it was free
Demolition reveals a damaged pipe or beamFixed urgently without taking a “before” photoClient questions whether the repair was actually needed
Cost is approved, but schedule impact is notNobody updates the delivery dateClient demands the original completion date despite extra scope
Changes are scattered across WhatsApp voice notesNo central log of approved extras per projectLine items are forgotten at final billing

Hidden technical issues vs. client scope changes

Before speaking with the owner, classify the situation:

  1. Hidden condition or unforeseen technical issue: Anything behind tile, under flooring or above a ceiling that was impossible to inspect during quoting (corroded galvanized pipe, structural dampness, non-compliant wiring). Here, photo documentation taken before touching the area is mandatory.
  2. Scope or specification change: The client changed their mind on a finish, asked to demolish an extra partition or added custom cabinetry. The rule is simple: no materials are ordered and no crew is assigned without an approved change order.

The 4-step protocol to approve change orders without friction

1. Document the finding or request on the spot

Take two clear photos with date and location stamps, and write a three-line description of what was found or requested.

2. Price direct cost, overhead and schedule impact

Never quote off the cuff on a noisy job site. Calculate materials, subcontractor labor, management fee and how many working days the change adds to the schedule.

3. Send a one-page change order marked “Pending approval”

Give the client a clear, concise summary:

Change order fieldIllustrative example
Project & IDApt 802 — Change Order #03
ReasonOwner request: illuminated niche in main shower
Scope includedWall chase, waterproofing, tile work and LED strip
Total price (COP)$1,450,000 + VAT
Schedule impact+2 working days added to completion date
Payment terms50% upon approval · 50% upon item completion

4. Get it signed on the phone before executing

With Obrity’s electronic signature, the owner approves from their phone with a verification code and timestamp under Colombia’s Law 527 of 1999. The signed record stays attached to the project alongside the before-and-after photos.

How we handle it in Obrity

Obrity keeps original scope separate from change orders so both your team and your client see what is approved, how much it adds and how each room is progressing. Explore our field solutions or book a demo to see it with your own projects.

Key takeaways

  • The mistake that destroys the most margin in remodeling is executing a verbal change request and trying to bill for it at the end of the project.
  • Always distinguish between a hidden technical condition (corroded pipe found during demolition) and a scope change requested by the homeowner.
  • No extra work should start without four items: photo of the condition, clear scope and price, schedule impact and written client approval.
  • In Colombia, an electronically signed change order has full legal validity under Article 7 of Law 527 of 1999.

Frequently asked questions

Is a client's WhatsApp message saying 'go ahead' enough to bill for extra work?

It depends on whether it states the exact price and scope. If the client only approves the idea without seeing the cost or extra days, disputes almost always arise at final billing. Formalizing each change order with price, timeline and signature prevents that conflict.

What is the difference between an unforeseen condition and a client addition?

It's a difference of origin: an unforeseen condition is a hidden technical issue that could not be seen before demolition (such as corroded plumbing or structural moisture), whereas an addition is a new request from the owner (upgrading tile or moving an outlet).

Are electronic signatures legally valid for change orders in Colombia?

Yes. Article 7 of Law 527 of 1999 recognizes electronic signatures in data messages as long as the method reliably identifies the signer and fits the purpose of the document.

Back to the blog

Obrity

Put this into practice on your next project.

In 20 minutes we'll show you how it looks with your projects: progress, evidence, reports and AI agents.

Security verification

Download resource

For security and to deliver the verified template, enter your name and work email and complete the human check below.

Security Captcha

Verified secure download · Zero spam.